Blue Shield California

Blue Shield of California

Location

Woodland Hills, CA

Client

Blue Shield of California

Schedule

24 months Design thru Occupancy. September 2005 - September 2007

Size

133,000 usf

Scope

Developed and Implemented a Phased Master Plan Program to Downsize this Facility from a 12 Floor Occupancy to its current state of a 7 Floor Occupancy. Construction Phasing of Multiple Floors per year was implemented to achieve this goal. Coordination with Both Design and Engineering was paramount in this staff reduction and corporate infrastructure downsizing, all in efforts to coincide with lease terms and space forfeiture. In addition Server Room Equipment upgrades and redundancy was built into the program to properly keep in step with technology and provide continued uninterrupted support to Staff.

Details

  • Tenant Restack of 7 Floors
  • Revitalization of Tenant Areas
  • Replacement of Network Fiber Backbone
  • Implemented New Security System Locally & Statewide
  • FM 200 & FLS Systems Design & implementation